Dana reduces
operator dependency

Managing multi-variant axle assembly

$2bn turnover, 5000 employees in Pune

A line with 200+ variants is managed by a system where operator dependency for critical operations is reduced to zero through detailed operator guidance and poka-yokes.

The Challenge

Manage a multi-variant axle assembly line with complex shim selection operations involving multiple, dynamic calculations.

How Did We Do This?

  • By implementing ODIN Workstation on the entire line.
  • By developing code and logic to transfer specific data from specific stations and calculate the shim values.

Benefits

  • Customer was able to balance the line cycle time by analysing operator cycle time data.
  • Customer used the data recorded for operations like tightening, leak testing and gauging to determine product quality trends.

Results

  • ODIN Workstation made adding new variants easy, without touching the PLC.
  • Dana was able to train new operators using the operator guidance system.

Featured Product

Read More Success Stories

Mercedes-Benz enhances engine assembly

Introducing traceability, end-of-line quality station

Electra EV improves existing line

Setting up a full traceability solution

Bharat Forge’s dynamic production

Developing a secure process sequence

Hanon puts quality to the test

Ensuring 100% traceability of testing parameters